My understanding from someone that builds these things is maybe 1 outta 4 actually make from start to finish when announced. I heard the one in Lowndes, and there was talk of one in Hale/ Marengo won’t might not break ground due to not having the amount of power needed to supply the data center.
I think Lowndes center will move forward. The one in Hale/Marengo got quite all of the sudden. I also think someone opened their mouth too soon on that one. Maybe that’s why the silence now.

He said the biggest driver is having a transmission line that CAN supply the amount of power needed. He also said that is like finding a needle in a haystack. When you find it, you struck gold.